Lobato Trestle Work
Work on the Laboto trestle pushes on as the season is less than a month away now. Arrival of all of the replacement girders and the multiple cranes means that the real work can now get under way. The construction crew has begun the removal of the chared timbers and the building of an extensive scaffolding to make the required repairs. The construction crew has also graded a road that runs down to the edge of the trestle. Work on the cement foundations in the creekbed is also underway. Along with getting a complete rebuild, the trestle will get a fresh new coat of paint. A metalic silver color. The completion of the trestle will mark an important achievement in the railroads history.